Mill Basin Bridge Project Update

 In News

Mill Basin is working on steel erection in channel and the north side of the project. Work to close in the Eastbound Bridge will be complete by Memorial Day 2017. The Westbound Bridge will be complete in July 2017.

On the south side of the project MBBC is completing the concrete and asphalt paving.

On the north side of the project drainage is complete. The MSCE wall has been completed. Concrete pavement will begin in May. Pavement will continue through the spring and be complete in early summer.

Targets to open the Eastbound Bridge is Labor Day 2017. Target to open both directions of the bridge is Thanksgiving 2017.