LaGuardia Airport Project Update

 In News

The two vertical images are of the Tully Construction crews setting precast box culvert sections for Work Order 203B.  Stages 1 and 2 (of 8 total) were completed this week – 6/15/17.  The work includes the installation of an increased capacity box culvert and RCP drainage system to increase the drainage capacity of the east end of the airport draining to Pump House 4.

The two  horizontal images are of the finished product of the East Field Lighting Vault that Joe Kreppein has been working on – Work Orders 102/104.  Work to commission and finalize building systems will be complete within the next two weeks.  The East Field Lighting Vault provides power and controls for all runway lights and signs for Airport Runway 13/31 and all associated taxiways.